Using TFS 2013 Web Interface...
Our company is new to TFS and I am doing a post-mortem on one of our first completed projects. I am looking to compare the original estimates on the tasks to the actual hours (as they've been logged in a separate time tracking system). However, since all of the tasks are in a "done" state, I can't seem to query any of the original estimates.
If I go into each individual ticket, I can look at the history, and see the original estimates (in the field "Remaining Work") but now that the tickets are done, the remaining work is obviously 0.
Is there a way to query to original values in the remaining work field (as they were when the ticket was originally created)?